Project: RANS21RB   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Randall Brooks   -  
Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:1990
Total Flight Time:
Start/Last Date:Apr 03, 2021 - No Finish Date
Engine:Titan IO-340 180HP
Propeller:Whirlwind
 
Friendly URL: https://eaabuilderslog.org?s=RANS21RB

Home or Last Project Picture

Apr 28, 2023     Flap gap seals and prep for wing removal - (2.5 hours) Category: Fuselage
Fit and trimmed flap gap seals. Located and drilled for nutplate install. Removed wing tips, ailerons, flaps and doors in prep for wing removal tomorrow. All fairings, gap seals, skylight and windshield have been fit.
 